Case Studies

CLIENT: Former Gas Works

By September 21, 2020 No Comments

SITE: Former Gas Works, Wigan

PROPOSALS:

Review of available information as part of an initial site appraisal and cost feasibility assessment.

BRIEF:

BEK has been commissioned to provide a full geo-environmental appraisal of the former gas works site. The works undertaken by BEK include:

BEK WORK:

– Preliminary Risk Assessment/Desk Study
– Intrusive Site Investigation Works (Boreholes and Trial Pits)
– Gas/Groundwater Monitoring
– Regulatory Liaison (Environment Agency and Local Authority)
– Quantitative Risk Assessment
– Preparation of a Construction Environment Management Plan
– Noise & Vibration Monitoring
– Air Quality Monitoring
– Remediation Options Appraisal
– Validation and regulatory sign-off